City of Woburn 2022 Paving Projects

Contractors for the city of Woburn will begin our 2022 paving projects.  D & R Contracting will begin milling operations on Monday morning followed by structures and then repaving. Contractors for the city are currently working on raising structures and hope to begin repaving streets this Saturday 10/1/2022.

There will be Woburn Police officers and DPW personnel on site during construction.
There may be times when access to your property may be limited if you need access or have issues please let on site police or DPW staff know they will assist you in resolving issue.
Any property adjustments will be done when all paving is complete please be patient.

The current schedule will be

Saturday 10/1
Pleasant St
Warren Ave
Warren Rd
Arlington Rd
Monday 10/3
Janis terr
Roman Rd
Howard Ct
Perry St
Wednesday 10/5 (Afternoon)
Winn Ct
Place Ln
Thursday 10/6
Garden Dr
Garden St
First Rd
3rd Rd
8th Rd

This tentative schedule is weather permitting and we will keep you updated on any changes.

Please check back to this webpage for an updated paving schedule.

You may contact the DPW at 781-897-5980 if you need assistance.

 

Feedback