Detours & Construction

  • Proposed Construction
  • Rerouted Traffic
  • Road Closed
  • Slow Delay
  • Under Construction
  • Utility Repair
Showing currently active detours. For more information, you can interact with the marked sections on the map. Scheduled detours will appear below.

Utility reconstruction in preparation for the replacement of the Salem Street Bridge is currently underway. Expect lane restrictions and delays in the area.

Type: Under Construction

Contractors have begun work on Wildwood Ave, Winn and Russell Streets on the repaving project. This work is expected to last 4 weeks and my cause delays and road closures please aviod these areas if possible. The tentative schedule for this project is as follows

Below please find the anticipated CIR schedule, with work starting on Friday of this week:

 

June 7th Friday Lower catch basins on Wildwood Avenue; hand out notices for entire project.
June 10th Monday CIR on Wildwood; lower catch basins on Winn Street
June 11th Tuesday CIR on Wildwood Avenue; lower catch basins on Russell Road
June 12th Wednesday CIR on Winn Street
June 13th Thursday CIR on Winn Street; raise all structures on Wildwood Avenue for HMA
June 14th Friday CIR on Russell Street; raise structures on Wildwood Avenue for HMA
June 17th Monday Finish CIR on Russell Street; raise structures on Winn Street
June 18th Tuesday Finish raising structures on Winn Street
June 19th Wednesday Raise structure on Russell Street
June 20th Thursday Raise structures on Russell Street
June 21st Friday Raise structures on Russell Street
June 23rd or 24th Sunday or Monday night D&R will be paving Wildwood Avenue Sunday night and Winn                                                           Street on Monday night (confirmed, however, I told them Wildwood Avenue should be ready as early as June 19th, Wednesday).  Micro on Russell Street to be scheduled based upon weather conditions after June 21st.

Type: Rerouted Traffic

The MWRA will be doing exploratory excavations around their water lines in the Washington St. & Montvale Ave. area

Type: Utility Repair

Montvale ave widening project has begun the first part of this project will be work to the drainage system.

  • D&R’s subcontractor to continue drainage work between Albany Street and the east end of the project.
  • D&R’s sub will begin water/hydrant work at various locations
  • Eversource Electric has installed new utility poles and will begin moving the power lines.
  • Daigle Electric has begun installing foundations for new traffic signals at Washington & Central streets
  • Montvale Ave Drainage Work

Type: Rerouted Traffic

The City of Woburn is working to improve the sewer system.  CIP Project Sewer Rehabilitation’s is the second phase of the city’s Sewer Capital Improvement Program, which was designed to rehabilitate the city’s East Side wastewater collection system.  CIP Project 2 Sewer Rehabilitation’s were completed summer 2018.  Warranty re-test is performed, during a period of high groundwater, approximately one (1) year following trench-less rehabilitation’s.  Warranty re-test involves inspecting rehabilitated sewers and sewer manholes and correcting any deficiencies that are identified.  Warranty re-test for CIP Project 2 Sewer Rehabilitation’s is scheduled to start Monday, April 29th and will take as many as five (5) weeks to complete.  CIP Project 2 Sewer

Rapid Flow Inc. is scheduled to continue retest inspection as part of the CIP Project 2 Rehabilitations in Woburn. They will begin work at 7:00 AM starting Monday, June 3. This week they plan to send one (1) lateral grouting retest crew. Rapid Flow will also send one (1) lateral lining inspection crew at some point at some point in the week. Work will be performed on the following streets:

 

ALBANY STREET EASTERN AVENUE ERIE STREET FULTON STREET GARFIELD AVENUE
GRAPE STREET GREEN STREET HIGHLAND STREET JEFFERSON AVENUE MONTVALE AVENUE
MOUNT PLESANT STREET ORANGE STREET PROSPECT STREET SOUTH STREET UNICORN DRIVE
UTICA STREET WASHINGTON STREET ARLINGTON STREET BELMONT STREET SPRING COURT TERRACE

 

Rapid Flow will also be repairing defects found in cementitious lined manholes at some point during the week. This work will be performed on the following streets:

 

ALBANY STREET ARLINGTON STREET BELMONT STREET EASTERN AVENUE GARFIELD AVENUE
GREEN STREET JEFFERSON AVENUE MONTVALE AVENUE MOUNT PLEASANT STREET ORANGE STREET
PROSPECT STREET SPRING COURT TERRACE SUMMER STREET

 

Type: Utility Repair