Detours & Construction

  • Proposed Construction
  • Rerouted Traffic
  • Road Closed
  • Slow Delay
  • Under Construction
  • Utility Repair
Showing currently active detours. For more information, you can interact with the marked sections on the map. Scheduled detours will appear below.

Leonard ST. Crew will be preparing for the main connection next week and then about a week of services. About 2 weeks left on this project.

 

Cedar, Salem and Washington St. Crew is about done with main and will be moving into the intersection @ Cedar and Washington this next week.  About 4-5 weeks remaining on this project.

 

Upcoming- Beacon St and Pleasant St.

US Pavement is planning on gearing up to create the right hand turn lane and complete the paving work on the following schedule

 

Curb Work – Turn Lane

  • Monday September 9th – Friday September 13th

 

New Paving Mill and Overlay

  • Saturday September 21st

 

Line Painting

  • Sunday September 22nd

Utility reconstruction in preparation for the replacement of the Salem Street Bridge is currently underway.

The contractor has begun Stage 1 bridge construction.

Week Ending (W/E) 06/29/19: Temporary frames (falsework) have been constructed on both sides of the bridge to support the Stage 1 Piles. There are 2 Piles on each side; each pile is 105- feet long.

W/E 07/05/19: Short week due to the Holiday. Contractor has staged its equipment and set piles for driving operations in the next week. The contractor used the pile’s actual weight and a vibratory hammer to position the piles in the ground.

W/E 07/12/19: Contractor will continue setting piles and staging the equipment. Contractor is scheduled to begin pile driving operations on Thursday and complete on Friday (one day each side). Please note that pile driving is a loud operation. The work is being conducted during the day to minimize disruptions to residential abutters.

W/E 07/19/19: Contractor will cut the piles to their final length, remove the falsework and demobilize its pile driving equipment from the project site. Contractor is scheduled to begin concrete form-work and rebar installation for the proposed bridge abutments on each side of the bridge.

W/E 07/26/19:  Contractor will continue concrete form-work and rebar installation.

Please note that the schedule for this work is weather dependent and subject to change without notice.

Expect lane restrictions and delays in the area.

Type: Under Construction

Contractors have begun work on Wildwood Ave, Winn and Russell Streets on the repaving project. This work is expected to last 4 weeks and my cause delays and road closures please aviod these areas if possible. The tentative schedule for this project is as follows

Below please find the anticipated CIR schedule, with work starting on Friday of this week:

 

June 7th Friday Lower catch basins on Wildwood Avenue; hand out notices for entire project.
June 10th Monday CIR on Wildwood; lower catch basins on Winn Street
June 11th Tuesday CIR on Wildwood Avenue; lower catch basins on Russell Road
June 12th Wednesday CIR on Winn Street
June 13th Thursday CIR on Winn Street; raise all structures on Wildwood Avenue for HMA
June 14th Friday CIR on Russell Street; raise structures on Wildwood Avenue for HMA
June 17th Monday Finish CIR on Russell Street; raise structures on Winn Street
June 18th Tuesday Finish raising structures on Winn Street
June 19th Wednesday Raise structure on Russell Street
June 20th Thursday Raise structures on Russell Street
June 21st Friday Raise structures on Russell Street
June 23rd or 24th Sunday or Monday night D&R will be paving Wildwood Avenue Sunday night and Winn                                                           Street on Monday night (confirmed, however, I told them Wildwood Avenue should be ready as early as June 19th, Wednesday).  Micro on Russell Street to be scheduled based upon weather conditions after June 21st.

Type: Rerouted Traffic

The MWRA will be doing exploratory excavations around their water lines in the Washington St. & Montvale Ave. area

Type: Utility Repair

Montvale ave widening project has begun the first part of this project will be work to the drainage system.

  • Daigle Electric has begun installing foundations for new traffic signals at Washington & Central streets
  • Montvale Ave Drainage Work
  • Road widening between Washington & Albany
  • Install mast arm foundation at Washington & Montvale
  • Begin curbing & sidewalk work
  • Eversource Electric has installed new utility poles and will begin moving the power lines

Type: Rerouted Traffic

The City of Woburn is working to improve the sewer system.  CIP Project Sewer Rehabilitation’s is the second phase of the city’s Sewer Capital Improvement Program, which was designed to rehabilitate the city’s East Side wastewater collection system.  CIP Project 2 Sewer Rehabilitation’s were completed summer 2018.  Warranty re-test is performed, during a period of high groundwater, approximately one (1) year following trench-less rehabilitation’s.  Warranty re-test involves inspecting rehabilitated sewers and sewer manholes and correcting any deficiencies that are identified.  Warranty re-test for CIP Project 2 Sewer Rehabilitation’s is scheduled to start Monday, April 29th and will take as many as five (5) weeks to complete.  CIP Project 2 Sewer

Rapid Flow Inc. is scheduled to continue retest inspection as part of the CIP Project 2 Rehabilitations in Woburn. They will begin work at 7:00 AM starting Monday, June 3. This week they plan to send one (1) lateral grouting retest crew. Rapid Flow will also send one (1) lateral lining inspection crew at some point at some point in the week. Work will be performed on the following streets:

 

ALBANY STREET EASTERN AVENUE ERIE STREET FULTON STREET GARFIELD AVENUE
GRAPE STREET GREEN STREET HIGHLAND STREET JEFFERSON AVENUE MONTVALE AVENUE
MOUNT PLESANT STREET ORANGE STREET PROSPECT STREET SOUTH STREET UNICORN DRIVE
UTICA STREET WASHINGTON STREET ARLINGTON STREET BELMONT STREET SPRING COURT TERRACE

 

Rapid Flow will also be repairing defects found in cementitious lined manholes at some point during the week. This work will be performed on the following streets:

 

ALBANY STREET ARLINGTON STREET BELMONT STREET EASTERN AVENUE GARFIELD AVENUE
GREEN STREET JEFFERSON AVENUE MONTVALE AVENUE MOUNT PLEASANT STREET ORANGE STREET
PROSPECT STREET SPRING COURT TERRACE SUMMER STREET

 

Type: Utility Repair