Road Work

We do our best to notify residents of upcoming and current road work. Weather conditions and unexpected emergencies may modify our plans.
September 4, 2026

Sewer maintenance work will be conducted on Middle Street, Mishawum Road and Susan Terrace from September 8 – 11, 2026. They will be working 7 am – 5 pm. During this time expect lane closures and slower than usual traffic flow.

Sewer maintenance work will also be conducted on Bennett Street from September 8 – 11, 2026 7 am – 5 pm. On Bennett Street there will be parts off the road closed to traffic during work.

August 19, 2026

Please be advised that the following roads below are expected to be paved. The work is expected to be completed by D&R General Contracting with assistance from Public Works; weather dependent.

Work will be done on Thursday August 20th 2026

  • New Boston Street (Merrimac to Presidential)
  • Pento Road (Stoneham Town Line to Mill St.)
August 17, 2026

Paving operations will be conducted on Russell Street starting at the Lexington line at 5 am on Wednesday, August 19th. Please expect significant delays and avoid Russell Street.

August 12, 2026

Wood Street is closed to traffic at both ends (Salem and Montvale) due to a downed utility pole. Crews are working to safely address the issue.

West Dexter is closed for sewer work. The road will be reopened by the end of the day.

July 24, 2026

Sewer maintenance work will be completed on the following streets beginning July 27 – 30, 2026. Work is expected to be done 7 am – 5 pm. The road will be open during work but expect delays as it will be brought down to one lane while manholes are open.

Albany Street

Ashburton Avenue

Barbara Circle

Beach Street

Buttaro Road

East Dexter Avenue

Forest Park Road

Highet Avenue

Hilltop Terrace

Main Street

Middle Street

Milan Avenue

Mishawum Road

North Maple Street

Presidential Way

Richard Circle

Richmond Avenue

Rumford Park Avenue

Salem Street

School Street

Westview Terrace

West Dexter Avenue

Wheeling Avenue

 

July 13, 2026

A section of Bedford Road (highlighted in red in the picture below) between Elijah Street and Houghton Street will be closed 7/13 – 7/17 to complete drainage work for the Hurld Park project. During the work, traffic on Bedford Road will be directed down either Elijah Street or Houghton Street. The work is expected to take place the entire week next week (7/13-7/17).

July 9, 2026

Winn Street in Burlington is being paved. Due to the proximity to Woburn, we’re sharing the Burlington paving page with you. https://www.burlington.org/m/newsflash/Home/Detail/299

June 18, 2026

Nightly Closures of I-95 (Route 128) Northbound Ramp onto Washington Street (Exit 54) Sunday, June 21, through Thursday, June 25, from 11:00 p.m. to 5:00 a.m. the following morning

The Massachusetts Department of Transportation (MassDOT) is announcing nightly closures of the I-95 (Route 128) northbound ramp onto Washington Street (exit 54).  The closures will begin on Sunday, June 21, from 11:00 p.m. to 5:00 a.m., the following morning and will continue each night through Thursday, June 25. The closures are necessary to safely and effectively allow crews to install traffic data collection cabinets and loop detectors.

During the temporary closures, the following detour will be in place:

I-95 (Route 128) northbound, exit 54 ramp to Washington Street:

  • Motorists on I-95 (Route 128) northbound will be directed to exit 55B onto I-93 northbound.
  • Motorists will be immediately directed to take exit 28A onto I-95 (Route 128) southbound.
  • Motorists will continue on I-95 (Route 128) southbound until they are directed to the exit 54 ramp for Washington street.

Drivers traveling through the area should expect delays, reduce speed, and use caution.

All scheduled work is weather dependent and subject to change without notice.

For more information on traffic conditions, travelers are encouraged to:

  • Download the Mass511 mobile app or visit www.mass511.com to view live cameras, travel times, real time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions
  • Dial 511 and select a route to hear real time traffic conditions.
  • Follow @MassDOT on X (formerly known as Twitter) to receive regular updates on road and traffic conditions.

June 11, 2026

Nightly Closures of I-95 Northbound (Route 128) Ramp to I-93 Southbound (Exit 55A)

Nightly closures, Sunday, June 14, through Tuesday, June 16, from 11:00 p.m. to 5:00 a.m. the following morning

The Massachusetts Department of Transportation (MassDOT) is announcing an overnight ramp closure of the I-95 (Route 128) northbound ramp onto I-93 southbound.  The closure will begin on Sunday, June 14, from 11:00 p.m. to 5:00 a.m., the following morning and will continue each night through Tuesday, June 16. The closure is necessary to safely and effectively allow crews to perform pavement milling operations.

During the temporary closure, the following detours will be in place:

I-95 northbound (Route 128), exit 55A ramp to I-93 southbound:

  • Motorists will be detoured to continue on I-95 northbound and take the exit 55B ramp onto I-93 northbound.
  • Motorists will then be detoured to take exit 28B ramp onto I-95 (Route 128)
  • Motorists will complete the detour by taking exit 55A ramp onto I-93 southbound.

Drivers traveling through the area should expect delays, reduce speed, and use caution.

All scheduled work is weather dependent and subject to change without notice.

For more information on traffic conditions, travelers are encouraged to:

  • Download the Mass511 mobile app or visit mass511.com to view live cameras, travel times, real time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions
  • Dial 511 and select a route to hear real time traffic conditions.
  • Follow @MassDOT on X (formerly known as Twitter) to receive regular updates on road and traffic conditions.

May 26, 2026

 Overnight Closures of I-93 Southbound Ramps and I-95 Southbound (Route 128) Ramps

Overnight closures, Wednesday, May 27, from 11:00 p.m. to 5:00 a.m. the following morning

WOBURN – The Massachusetts Department of Transportation (MassDOT) is announcing overnight alternating ramp closures at the following locations: I-93 southbound onto I-95 southbound (Route 128) exit 28B ramp, I-95 southbound (Route 128) exit 54 Washington Street ramp, and the I-95 southbound (Route 128) exit 53 Route 38 ramp. The closures will begin Wednesday, May 27, from 11:00 p.m. to 5:00 a.m., the following morning. The closures are necessary to safely and effectively allow crews to perform milling operations.

Only one ramp will be closed at a time.

During the temporary closures, the following detours will be in place:

I-93 southbound, exit 28B ramp to I-95 (Route 128) southbound:

  • Motorists on I-93 southbound will be directed to continue onto exit 28A for I-95 (Route 128) northbound.
  • Motorists will be directed to take exit 55B onto I-93 northbound where they will be immediately directed to take exit 28B onto I-95 (Route 128) southbound

I-95 (Route 128) southbound, exit 54 ramp to Washington Street:

  • Motorists on I-95 (Route 128) southbound will be directed to exit 53 (Route 38).
  • Motorists will go around the traffic circle and take the on-ramp for I-95 (Route 128) northbound.
  • Continue on I-95 (Route 128) northbound to exit 54 for Washington Street.

I-95 (Route 128) southbound, exit 53 ramp to Route 38:

  • Motorists on I-95 (Route 128) southbound will be directed to continue onto exit 52 Winn Street.
  • Motorists will then be directed to take a left at the end of the ramp onto Winn Street and then be directed to take the ramp onto I-95 (Route 128) northbound.
  • Motorists will continue on I-95 (Route 128) northbound and be directed to take exit 53 onto route 38.

This work is part of a $14.3 million interstate pavement preservation project on I-95 (Route 128) in Woburn.

Appropriate signage and law enforcement details will be in place to guide drivers through the work area.

Drivers traveling through the area should expect delays, reduce speed, and use caution.

All scheduled work is weather dependent and subject to change without notice.

For more information on traffic conditions, travelers are encouraged to:

  • Download the Mass511 mobile app or visit www.mass511.com to view live cameras, travel times, real time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions
  • Dial 511 and select a route to hear real time traffic conditions.

Follow @MassDOT on X (formerly known as Twitter) to receive regular updates on road and traffic conditions.

May 19, 2026

National Grid work at Pine St, Central St. and Orange St.

This is an important notice informing you National Grid will be working in your neighborhood on Pine St from Perry St to Central St; Central St from Pine St to Utica St; and Orange St from Central St to #33 in order to replace and/or relocate the gas main. The work will begin on or about May 20th, 2026, and will continue for approximately 12 weeks. Work will generally take place from 7:00am to 4:00pm, Monday – Saturday.

National Grid customers, within the scope of the project, will have their gas services replaced and transferred to the new gas main in the street. Each gas service transfer will be scheduled in advance with the customer and they can expect a short interruption of gas service on the day of the work on the service. The customer will need to allow our contractor and company technician’s access to the property in order to restore the gas service. We apologize in advance for any inconvenience, but this project is part of our commitment to provide continuous improvements and keep the natural gas delivery system safe and reliable. National Grid and/or a qualified contractor (RJ Devereaux Corp) will perform the work. A police detail will be provided. The road will be open to the public and parking may be limited. Expect delays and please use an alternate route if possible. A construction foreman with appropriate identification will be on site to address your parking needs throughout the duration of the project.

If you have any questions about the project, please call National Grid Customer Service 24/7 at 1-800-233-5325.

 

April 22, 2026

Horn Pond Parking Lot off of Lake Avenue

Over the next few weeks there will be construction work to upgrade the Horn Pond Parking Lot. We will do our best to minimize disruption to existing parking spaces, but there may be times when some spaces will be unavailable.

March 20,2026

MassDOT is reporting: Nightly Ramp Closures at I-93 Southbound (Exit 28B) to I-95 (Route 128) Southbound

Nightly closures, Tuesday, March 24, and Wednesday, March 25, from 11:00 p.m. to 5:00 a.m. the following morning

WOBURN – The Massachusetts Department of Transportation (MassDOT) is announcing nightly closures of the I-93 southbound ramp (exit 28B) to I-95 (Route 128) southbound in Woburn.  The closures will take place on Tuesday, March 24, and Wednesday, March 25, from 11:00 p.m. to 5:00 a.m. the following morning.  The closures are necessary to safely and effectively allow crews to perform drainage improvements.

During the temporary closures, the following detours will be in place:

I-93 southbound ramp (exit 28B) to I-95 (Route 128) southbound:

  • Motorists on I-93 southbound will be detoured to exit 28A for I-95 (Route 128) northbound.
  • Motorists will then be directed to take exit 55B to I-93 northbound.
  • Continue on I-93 northbound to exit 28B to access I-95 (Route 128) southbound.

This work is part of a $14.3 million interstate pavement preservation project on I-95 (Route 128) in Woburn.

Appropriate signage and law enforcement details will be in place to guide drivers through the work area.

Drivers traveling through the area should expect delays, reduce speed, and use caution.

All scheduled work is weather dependent and subject to change without notice.

For more information on traffic conditions, travelers are encouraged to:

  • Download the Mass511 mobile app or visit www.mass511.com to view live cameras, travel times, real time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions
  • Dial 511 and select a route to hear real time traffic conditions.
  • Follow @MassDOT on X (formerly known as Twitter) to receive regular updates on road and traffic conditions.

March 13, 2026

There is a water main break in front of 85 Willow Street that may impact traffic. Crews are on-site working to address the issue. Please plan extra caution in that area.

January 8, 2026

There is a water main break on Montvale Ave at the Rt 93 South bound on-ramp. Crews are working to repair the leak. Expect delays.

 

December 31, 2025

Route 93 Exit Ramp 28B

Nightly Ramp Closures at I-93 Southbound (Exit 28B) to I-95 (Route 128) Southbound

Nightly closures, Sunday, January 4, through Saturday, January 10, from 11:00 p.m. to 5:00 a.m. the following morning

  

WOBURN – The Massachusetts Department of Transportation (MassDOT) is announcing nightly closures of the I-93 southbound exit 28B ramp to I-95(Route 128) southbound. The closures will be in effect nightly from Sunday, January 4, through Saturday, January 10, from 11:00 p.m. to 5:00 a.m. the following morning.  The closures are necessary to allow crews to safely and effectively perform tree trimming along the roadway.

 

During the temporary closures, the following detours will be in place:

I-93 southbound exit 28B on-ramp to I-95 (Route 128) southbound:

  • Motorists on I-93 southbound will be detoured to exit 28A for I-95 (Route 128) northbound.
  • Motorists will then be directed to take exit 55B to I-93 northbound
  • Continue on I-93 northbound to exit 28B to access I-95(Route 128) southbound.

This work is part of a $14.3 million interstate pavement preservation project on I-95(Route 128) in Woburn.

Appropriate signage and law enforcement details will be in place to guide drivers through the work area.

Drivers traveling through the area should expect delays, reduce speed, and use caution.

All scheduled work is weather dependent and subject to change without notice.

For more information on traffic conditions, travelers are encouraged to:

  • Download the Mass511 mobile app or visit www.mass511.com to view live cameras, travel times, real time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions
  • Dial 511 and select a route to hear real time traffic conditions.
  • Follow @MassDOT on X (formerly known as Twitter) to receive regular updates on road and traffic conditions.

November 21, 2025

Mill Street will be closed for milling/paving during the day 7 am – 4 pm Friday November 21st through Tuesday November 25th.

October 24, 2025

Cedar Street will be paved 10/24 starting at 10pm.  We anticipate that they should be off the road by 7 am on Saturday, October 25th.

October 15, 2025

The water department will be working at 167 Winn Street on October 16, 2025.

In addition, milling work will be done on the following streets in preparation for paving. While we will do our best to keep traffic flowing, please plan extra time to travel these roads during the milling process.

Thursday 10/16 Friday 10/17 Monday 10/20 Tuesday 10/21
Street From To Sq. Yds.
Townsend St Mountain St Kearsarge Ave 652 652
Kearsarge Ave Lamoile St Townsend St 960 960
Lamoile St Kearsarge Ave Dead End 689 689
Tennessee St Wheeling St Dead End 980 980
East Dexter St Chester Ave Longwood Ave 1667 1667
Cedar St Washington St Stoneham T/L 8906 4000 4906
Grape St Central Street Washington St 1760 1760
Erie St Washington St Henshaw St 2897 2897
Allen St Green St Spring Court 2040 2040
Spring Court Green St Spring St Terr 2618 2618
Leonard St Blueberry Hill Rd Dead End 1682 1682
Skyview Rd Blueberry Hill Rd Skyview Lane 1583 1583
Skyview Lane Skyview Rd Cul-de-sac 2785 2785
Acorn St Willow St Cul-de-sac 1572 1,572
Pond Terrace Crawford Drive Cul-de-sac 2376 2,376
Loves Lane Crossman Rd Dead End 1818 1,818

September 9, 2025

School Street and Merrimack Street

Weather permitting, paving will be done on Saturday, September 13th. Work being completed by Newport Construction Corporation.

August 15, 2025

Mishawum and Clinton Street

National Grid is replacing the natural gas main at 37 to 59 Mishawum RD.; 29 to 36 Clinton ST., .As part of this project, we will also replace the natural gas service piping that connects the main to the customer’s gas meters.

Detours may be necessary during the work. Construction is expected to begin on August 18, 2025, and anticipated to last to November 14, 2025 weather permitting.

 

August 1, 2025

Country Club Road

Beginning Monday, August 4th, crews will be working at Country Club Road for two days. Traffic will be able to pass but expect some delays.

 

June 25, 2025

Russel Street & Green/Nashua

On June 26 paving will begin on Russell Street beginning at 5am. The crews will be paving the street from the area of Moreno Drive to Gayle Street. The work is expected to go into the afternoon hours.

Paving work will also start at 5 am June 26 at Green/Nashua and follow same order as milling going east to west ending at Belford Circle.

Please avoid these areas if at all possible. The work will cause significant travel delays

June 24, 2025

Horn Pond Area

As part of the City’s Complete Streets Program, construction will begin on pedestrian safety improvements adjacent to Horn Pond.  Work is scheduled to begin July 7, 2025 (delayed from June 27, 2025). There are two primary locations as part of this project.

Location 1 includes the entrance to the public parking lot at Horn Pond to improve pedestrian safety in that area.  Location 2 is the intersection of Hudson Street and Arlington Road and includes the removal of one crosswalk, replacement of ADA ramps at the remaining crosswalks, and installation of flashing pedestrian beacons.

Work periods are generally between 7am and 3pm, Monday-Friday. Work duration of 1-2 weeks per location. During construction delays are to be expected but access will remain open. Please use caution when driving or walking in this area during construction.

View the plans here!

 

June 18, 2025

Traffic Advisory for Thursday, June 19th beginning at 7am.
In preparation for future paving, work crews will be grinding Russell Street from Moreno Drive to Gayle Street. The grinding will significantly impact traffic. Please seek alternate routes if possible and plan your travel time expecting delays.

June 17, 2025

D&R will commence milling June 18th at 5 am at Green and Nashua street. It is our hope that the early start will mitigate impact on commuter traffic at this busy intersection. We appreciate the neighborhood’s cooperation.

June 12, 2025

Beginning June 18th work will be done on Route 3 near the Winchester line. The work is being done primarily in Winchester, but it may impact your travel in the area as a portion of the work will be on the Woburn line.

June 2, 2025

School Street and Merrimack Street

Work being completed by Newport Construction Corporation. Schedule below may be modified due to weather conditions changing.

Drainage work to be done on: 6/2/2025 – 6/3/2025

Reclaiming and grading to be done starting: 6/6/2025

Binder will be done on 6/9/2025

Curb and sidewalks to be done starting Monday 6/11/2025 – 6/17/2025

Topcoat Paving: 6/23/2025

Pavement Markings 6/24/2025

May 29, 2025

A water main break at the intersection of Montvale and Central Street is under repair. Please avoid the area if you can.

 

From our neighbors in Burlington. Nocella Landscaping and Paving, will begin milling Wyman Street and Thistle Road on Thursday May 29th (weather permitting). Paving is scheduled for June 11th.

Map of road detours

 

May 14 2025

If possible, please avoid the intersection of Mishawum Road, Clinton Street, and Beach Street. There is a gas leak which is currently being worked on in the roadway.

 

April 21, 2025

State work to begin 4/22 on Route 3 & Lexington Street with a focus on pedestrian improvements.

The work area is identified in the image below.

Picture of Lexington street and 3A that will be worked on by state transportation agency

Additional details can be found here: Woburn locations Pages from District 4 609387 123633 12325 2023-2 (003) MA Work.

 

April 14, 2025

Ward Street Sweeping Schedule Set

Dates are subject to weather fluctuations

  1. Ward 7-1 & 7-2    4/14 – 4/23
  2. Ward 1-1 & 1-2    4/24 – 5/5
  3. Ward 3-1 & 3-2    5/6 – 5/15
  4. Ward 5-1 & 5-2    5/16 – 5/28
  5. Ward 6-1 & 6-2    5/29 – 6/9
  6. Ward 2-1 & 2-2    6/10 – 6/23
  7. Ward 4-1 & 4-2    6/24 – 7/3
Please see March 23rd update for downtown and major roadway schedule.

 

Horn Pond vegetation work by Eversource

Eversource will be conducting ROW vegetation work occurring behind STA 211 (Pond Street across from Well Park) the week of April 14th. Vegetation management will be brush cutting and chipping in the area west of STA 211, where the transmission lines enter into the substation. There are bike/walking paths which intersect the ROW at this location – part of the Horn Pond Recreation Area. The tree crews will have appropriate signage and the work zones will be marked. The work area is circled in yellow in the image below.

April 4, 2025

City of Woburn Water Department System Flushing – Zone 15

Starting Monday, April 7th, the City of Woburn Water Department will begin hydrant flushing the water system in Zone 15. This process is expected to last approximately 10 to 14 business days, weather permitting. Flushing will occur from 8:30 AM to 3:00 PM each day.

The flushing will start on Cambridge Road and extend north to the Burlington town line, then continue from Russell Street and Lexington Street west to the Lexington town line.

Residents and businesses in Zone 15 and surrounding areas may experience temporary water disruptions, including low pressure, brief loss of water, and/or discolored water. If you experience discolored water, running cold water faucets until the water runs clear is recommended.

For further information, or if you have questions, contact the Water Department at 781-897-5945.

 

April 2, 2025

National Grid has notified us that they are doing street restoration. The schedule below has been provided by National Grid and may change as conditions require. Street restoration may include milling and paving activities.

Schedule of roads and dates projected.

 

March 23, 2025

Sidewalk & Street Sweeping Main roads and Sidewalks. Schedule may adjust due to changing weather conditions. Additional street sweeping schedule to be finalized for non-main roads.

 The following roads are scheduled for street sweeping 3/24 – 3/31

  • Winn Street
  • Main Street (South)
  • Main Street (North)
  • Kilby Street
  • Pleasant Street
  • Arlington Road – Lake Ave
  • Warren Ave
  • Wyman Street
  • Lowell Street
  • Bedford Road
  • Locust Street
  • Willow Street
  • Russell Street
  • Green Street
  • Montvale Ave

The following roads are scheduled for street sweeping 3/31 – 4/7

  • Vernon Street
  • Bow Street
  • Wood Street
  • Pine Street
  • Salem Street
  • CentraI Street
  • Washington Street
  • Washington Circle
  • Upper Salem Street
  • Mishawum Road
  • Forest Park Road
  • Eaton Ave
  • Clinton Street
  • Middle Street
  • Beach Street

The following roads are scheduled for street sweeping 4/7 – 4/14

  • Wildwood Street
  • Olympia Ave
  • School Street
  • Alfred Street
  • Merrimac Street
  • Ryan Road
  • New Boston Street
  • Elm Street
  • Pearl Street
  • Winter Street
  • Ward Street
  • Traverse Street
  • Commerce Way

March 22, 2025 

Eversource to begin tree work the first week of April. 

As part of Eversource’s ongoing commitment to deliver reliable energy to customers, Eversource has contracted with qualified tree contractors to perform routine vegetation maintenance within the electric system rights of way  The work, which is scheduled to begin the first week of April, is part of Eversource’s continuing efforts to ensure reliable electric service to you and to thousands of homes and businesses throughout the region, especially during extreme weather events.

Why Tree Work is Important

  • To protect the electric system, we remove tall-growing species from the right of way and cut branches extending into the right of way. These trees and branches pose a serious safety hazard, now or in the future, if they contact energized equipment.
  • Vegetation contact with electric facilities may lead to power outrages that could impact thousands of electric customers. The clearing of trees and branches in and along the right of way will improve system performance, especially during severe weather events.

Work in Your Neighborhood

The vegetation management work may include:

  • Clearing of incompatible trees and/or removal of branches that are encroaching into the right of way.
  • Removing tall-growing tree species that are incompatible to the transmission system, using manual climbing crews or mechanical tree-harvesting equipment, and tree-chipping machinery.

What You Can Expect

We want you to know that this work will not interrupt electric service to your property. Work hours will typically be 7 am to 7 pm, Monday through Saturday. Due to weather or other unexpected circumstances, from time to time crews may need to work longer hours or on a Sunday.

In certain areas, this vegetation management scope may be more than what has been experienced in the past.

Based on the width of the right of way, the type and number of transmission lines, the location of the lines within the right of way and the topography, Eversource employs a “one-zone” vegetation maintenance method.  This method establishes the following:

  • One-zone maintenance occurs within a right of way wire zone, which is the area directly under the transmission lines, extending to the edge of the easement or the width of the maintained area. Eversource manages the wire zone to promote a low-growing plant community dominated by grasses, flowers, ferns and small shrubs under 3 feet in height at maturity. Within this zone, trees and brush are selectively removed to allow for the establishment and preservation of these native, low-growing plant communities in non-lawn areas. Only established compatible species with a mature height of 15 feet or less at maturity may be allowed to remain in the wire zone, depending on location. All other plants with a mature height greater than 15 feet will be removed.

 

The diagram illustrates a typical right of way condition. This work is occurring within the existing edge of clearing. Your neighborhood may have a different configuration of transmission structures.

 

Work Performance

Eversource is using approved contractors to conduct this work. The work may be completed in several stages, or at various times during the year. Work may also be performed by different contractors depending on the scope of work required in the particular right of way.  Trimming and tree removal is performed throughout the year.

 

Keeping the Wood from Cleared Areas

If you would like to keep the wood from trees cut on your property, please call 888-673-9943. The wood that is to be kept for your personal use will be placed along the edge of the maintained area within the right of way and outside of the wire zone and environmentally sensitive areas. Wood and cut branches not left for personal use will be chipped & removed, slashed, or diced and left within the right of way. Diced vegetation will not be left within access areas or within the cleared areas around structures and guy wires.  Debris will also be kept out of water courses, stream and river banks and bodies of water including standing water in wetland areas.

Additional Communication

Those with property in the area will be receiving a door hanger or email informing them of the scheduled work.

Please contact Eversource if you have a private water well within 100’ of the electric transmission right of way or with any questions you might have.  We can be reached at 888-673-9943 or MAVegMaintenance@eversource.com

 

March 14, 2025

Annual Water Flushing Begins March 17 2025

The City of  Woburn Water Department will begin flushing the city’s water system on Monday, March 17, 2025, and continue over the next few months. Flushing will take place on weekdays from 8:30 a.m. to 3 p.m. and will be carried out in zones to minimize any impact on water quality and service. Water will be flushed by releasing it from selected hydrants in each zone. Updates will be posted on this webpage, and RAVE phone alerts will be sent to affected residents and businesses as the program progresses.

Where Will Flushing Take Place?
Flushing will be done in zones to reduce the potential for water quality or service disruptions.

Flushing in Zone 1 and Zone 2 will begin on Monday, March 17th, and is expected to last about 14 business days, depending on weather conditions. Flushing will take place between 8:30 a.m. and 3 p.m. These zones include Lake Ave (the starting point), Cambridge Road, Lexington Street, Garden Street, Burlington Street, Pleasant Street, Arlington Road, Warren Ave, and parts of Main Street.

Residents and businesses, along with surrounding neighborhoods, may experience temporary loss of water, low water pressure, and/or discolored water.  If you experience discolored water, it is recommended that you run your cold water faucets until the water runs clear.   For more information please visit the City of Woburn website at www.woburnma.gov.   If you have any questions, please contact the Water Department at 781-897-5945. Thank you.

 

February 24th 2025

Snow removal operations will be conducted in Downtown Woburn on Main Street from High Street to Pleasant Street throughout the day, Monday February 24th, 2025. Work will begin as early as 3 am. During snow removal there will be no parking on either side of Main Street. Please look for no parking signs and give yourself extra time to travel through the downtown area.

We appreciate your cooperation. Crews are mindful of busy traffic times and will do their best to release parking spaces as each area is cleared.

 

February 14th 2025

Green Street & Eastern Ave

The water department is working to address a water main break at Green St and Eastern Ave.

February 7th 2025

Hinston & Edith

The water department will be working at Hinston and Edith to address a water leak. We apologize for any inconvenience.

 

January 18th, 2025

Hurld School Demolition (75 Bedford Road)

Hurld School demolition continues. Permission has been granted for the demolition contractor to work on Saturday January 18th beginning at 7 am. The work should have no impact on Bedford Road traffic flow, but neighbors may see work being done on site.

 

January 15th – 17th 2025

Pond Street

The Town of Winchester has notified us that work at 204 Pond Street will begin on Wednesday, January 15th.  This will require Pond Street to be closed from Brantwood Road to Arlington Road.  Some staging of equipment on Brantwood Road will take place prior to the project date. Please expect travel detours and delays in the area.

 

January 8, 2025

Roads are expected to remain open, but you may experience slowed traffic in the areas below. Please plan accordingly.

Green Street and Nashua

The first phase of the Green/Nashua Safety Project will be happening on Tuesday January 8th from 7AM-4PM. This work will include the removal of 2 trees that are on city property at the Green Street / Nashua Street intersection and the work will be done by the Woburn DPW department. There will be a police detail on Green Street all day to help with the traffic flow. We would highly recommend avoiding this area as traffic may build up at times and cause delays due to this work. We appreciate your understanding and cooperation as we work to enhance the safety of this area. Thank you for your attention on this matter.

Salem Street

National Grid is working on a leak at 115 Salem Street.

Feedback